RERA Statutory Handover Ledger • Dubai Law No. 8 & Civil Code Art. 880

Off-Plan Handover, Snagging & Completion Protocol

A rigorous, institutional-grade handbook for taking delivery of your Dubai property. Inspect 50 technical defect checkpoints, calculate net statement-of-account (SOA) outlays, and activate statutory 10-year structural warranties.

Statutory Protection
10 YearsArt. 880 Civil Code

Mandatory contractor structural liability + 1-year Defect Liability Period (DLP).

Book Certified Snagging Desk
Inspection Progress Monitor
0 of 22(0% Audit Completed)
Submit to Developer Care
CriticalHVAC

Thermostat Calibration & Ambient Delta-T

Verify thermostat setpoint matches actual output. Confirm 8°C–12°C delta between return and supply air.

MajorHVAC

Condensate Drain Slope & Overflow Pan

Pour 2L water into FCU drip tray to confirm zero pooling and unobstructed discharge into building riser.

MinorHVAC

Airflow Balance & CFM Balancing in Bedrooms

Ensure air supply diffusers provide even velocity without whistling or vibration rattling at max fan speed.

MinorHVAC

FCU Access Hatch & Filter Cleanliness

Ceiling access panel must align with filter track and motor for standard quarterly maintenance.

CriticalMEP

Distribution Board (DB) ELCB / RCD Trip Test

Press mechanical test buttons on all 30mA and 100mA residual current breakers; verify instant isolation.

CriticalMEP

Socket Polarity & Ground Earthing Impedance

Test all 13A 3-pin British standard sockets for live-neutral polarity and verified earth loop continuity.

MajorMEP

Smart Home Automation & Video Intercom Hub

Verify two-way audio, door release relay, and cloud Wi-Fi connectivity to building security gate.

MajorMEP

Cooker / Oven Isolator & High-Draw Load Lines

Check 45A dedicated radial cable gauge and isolator switch placement away from sink splash zones.

CriticalPLUMBING

Shower Floor Drainage Gradient (Minimum 1:80 Slope)

Run water for 5 minutes. Verify zero stagnant puddles around perimeter tiles and swift drain suction.

MajorPLUMBING

Concealed Cistern Leakage & Dual-Flush Pressure

Check internal overflow mechanism of wall-hung WC units to prevent silent ongoing water loss to DEWA bill.

MajorPLUMBING

Under-Sink Angle Valves & Flexible Hose Stress

Inspect vanity and kitchen sink stop valves for leaks, weeping joints, or over-twisted braided steel hoses.

CriticalPLUMBING

Water Heater Pressure Relief Valve (PRV) Runoff

Confirm heater safety valve discharge pipe terminates visibly into a floor waste without backflow.

CriticalJOINERY

Fire-Rated Entry Door Perimeter Acoustic & Intumescent Seal

Inspect self-closing mechanism, keyless digital lock latch, and smoke seals around 60-min rated door frame.

MinorJOINERY

Internal Door Clearances & Latch Mortise Alignment

Check 3mm gap consistency along jambs; verify zero dragging on carpet or porcelain tile thresholds.

MinorJOINERY

Built-in Wardrobe Soft-Close Hinges & Drawer Runners

Fully extend all drawer slides; ensure soft-close dampers engage smoothly without binding or rubbing.

MajorJOINERY

Kitchen Quartz / Marble Countertop Seamless Seams

Check mitred waterfall edges and hob cutouts for micro-fractures, silicone seal, and level plumb.

MajorFINISHES

Floor Porcelain / Marble Hollow Tile Acoustic Tap Test

Tap each tile with a non-marking acoustic sounding rod; flag hollow spots indicating insufficient mortar bed.

MinorFINISHES

Wall Plaster Smoothness & Paint Finish Under Raking Light

Inspect walls with a 2,000-lumen inspection lamp to identify plaster bumps, roller marks, or patching.

MinorFINISHES

Skirting Board Caulking & Mitered Corner Expansion

Verify flexible acrylic mastic along wall and tile interfaces without shrinkage gaps or peeling.

MajorFINISHES

Glazing Double-Pane Vacuum Seal & Scratch Inspection

Check floor-to-ceiling glass for condensation fog between panes, thermal stress cracks, or surface scratches.

CriticalBALCONY

Balustrade Rigidity & 1.5 kN/m Impact Compliance

Inspect toughened laminated glass or aluminum handrail anchoring to ensure zero deflection under load.

CriticalBALCONY

Balcony Waterproofing Membrane & Scupper Drain

Ensure rain and wash water drains away from sliding door threshold toward external drainage scuppers.

Professional Engineering Audit

Need an Accredited Third-Party Snagging Surveyor?

Equipped with FLIR thermal imaging cameras, socket polarity load meters, and laser levels. Average turnaround 24 hours with an official RERA-compliant punchlist.

Hire RERA Snagging Team
Handover Guidance & Warranty Rights

Frequently Asked Questions on Handover & Snagging

Key operational, statutory, and settlement guidelines for unit delivery.

What is the standard snagging process for off-plan property in Dubai?

Snagging is the formal technical inspection of an off-plan property prior to final settlement. It inspects all finishes, MEP (Mechanical, Electrical, Plumbing), HVAC cooling airflow, window seal integrity, joinery, and structural alignment. Under RERA regulations, developers must rectify all recorded defects within 14 to 30 days before keys are released.

How much are the settlement fees during handover in Dubai?

Handover settlement costs typically comprise: (1) Remaining purchase balance (e.g., 20% to 40% per payment plan), (2) DLD Title Deed fee (AED 290 total), (3) DLD Admin & Trustee fee (AED 4,000 + 5% VAT), (4) DEWA utility deposit (AED 2,000 for apartments / AED 4,000 for villas), (5) District cooling deposit (Empower/Tabreed approx. AED 1,000 to AED 2,000), and (6) First quarter advance service charges.

What warranties protect Dubai property buyers after handover?

Under UAE Civil Code Article 880 and RERA standards, developers provide: (1) A mandatory 1-year Defect Liability Period (DLP) covering all non-structural fixtures, joinery, MEP, and cosmetic defects; and (2) A 10-year Decennial Structural Warranty covering foundational and core architectural structural integrity.

How does Oqood convert into a Title Deed upon completion?

Upon issuance of the Building Completion Certificate (BCC) by Dubai Municipality and RERA, the pre-title deed registration (Oqood) is submitted to the Dubai Land Department (DLD) or a DLD Trustee Center for conversion into a permanent electronic and paper Title Deed (Milkiya) in the owner's name.

Can I appoint an independent snagging company in Dubai?

Yes. Most institutional buyers hire a certified independent third-party snagging inspection firm equipped with thermal imaging cameras, socket testers, moisture meters, and laser levels. The certified snagging report is formally submitted to the developer's customer care portal for rectification.

Private Client Handover Concierge

Taking Handover of an Off-Plan Property This Quarter?

BookMyOffPlan coordinates certified snagging engineers, DLD Trustee conveyance, and tenant placement so overseas buyers experience zero friction during delivery.